Roof truss renovation in 9 days: how it goes, day by day.

SDOMVEA team
IN BRIEF What happened each day – from removing the old roofing to the finished ridge.
Roof battening

Example: an older family house has its original roof truss with damaged wall plates and asbestos roofing, and the owners want metal roofing and a usable attic. This is how the replacement typically goes, day by day – it is a sample schedule; the real course depends on the scope and the weather.

Day 1 – removing the roofing

Asbestos roofing must not be broken or thrown. A specialist company packs it into labelled bags and takes it to a landfill. Meanwhile, scaffolding goes up and the building is covered with a tarpaulin.

Day 2 – 3 – removing the roof truss and new wall plates

The old truss comes down in sections. A common find: the ring beam under the wall plates is crumbled in places and has to be patched with concrete. You can’t see that during a site visit – which is why we keep a contingency in the budget.

Day 4 – 6 – installing the new roof truss

We prepare the new collar-beam truss from KVH beams in the workshop in advance, so on the roof it is just assembly. Kiln-dried KVH timber is dimensionally stable and doesn’t crack, unlike fresh sawn timber.

E-SHOP · 90 % IN STOCKOrder building materials onlineTimber, insulation, roofing and fasteners delivered to your site.To the e-shop →

Day 7 – membrane, counter-battens and battens

A vapour-permeable roofing underlay, counter-battens for ventilation and battens for the standing-seam metal. We deliver the material to the site in the morning.

Day 8 – 9 – roofing, gutters, ridge

Anthracite standing-seam metal, gutters, snow guards and a ventilated ridge. With a typical scope and good weather the roof is finished in 9 working days.

What it costs

An indicative roof price by area and roofing is shown by the calculator; you get the exact price after a site visit in an itemised quote. Insulation and finishing of the attic can follow in a later stage.

Planning a new roof? Roof inspection is free – we’ll get back to you as soon as possible.

Calculate your materials: Configurator: Roof measurement · Configurator: Roof build-up

Was this article helpful?
Written by the DOMVEA teamBuilders from Namestovo. We build houses, log homes and roofs across Slovakia and Czechia.What we build →